FY 18-19 CHIP SEAL PROGRAM

PROJECT NO.
SM 580 D
SCHEDULE
Starting April 15 and will last approximately 4 weeks
 
 
LOCATION
Lake Havasu City

TUESDAY - APRIL 23, 2019
STREET FROM/TO
BRIAR WAY TARPON DR to MISSION DR
CATTAIL DR YONDER DR to MISSION DR
CHERRY TREE DR MCCULLOCH BLVD to MISSION DR
CISCO DR N SMOKETREE AVE to EL DORADO AVE
EL TORO DR TARPON DR to JAMAICA BLVD
MISSION DR MCCULLOCH BLVD to CHESAPEAKE BLVD
MISSION WAY MISSION DR S to SLOOP DR
PELICAN DR TARPON DR to SWORDFISH DR
SLOOP DR MCCULLOCH BLVD to CHESAPEAKE BLVD
YONDER DR MCCULLOCH BLVD to TARPON DR
WEDNESDAY - APRIL 24, 2019
STREET FROM/TO
CARDINAL DR KIOWA AVE to CACTUS WREN DR
FREMONT DR CATARACT DR to ACOMA BLVD
GREEN DR JONES DR to ACOMA BLVD
LINDA DR CACTUS WREN DR to KIOWA AVE
MOCCASIN DR THUNDERBOLT AVE to ROLLING HILLS DR
OAK DR CYPRESS DR to CHIP DR
PASO DR ACOMA BLVD to FREMONT DR
SPRUCE DR WALNUT DR to OAK DR
WALNUT DR LAKE HAVASU AVE to CHIP DR

STATE ROUTE 95/RIVIERA PARKWAY INTERSECTION IMPROVEMENT PROJECT

This project is a widening project which will provide a new right hand turnbay, intersection lights, etc.

PROJECT NO.
PR2070
STATUS
Construction
 
SCHEDULE
November 2018 to May 2019
COST
$0.6M
LOCATION
State Route 95/Riviera Parkway Intersection

ROTARY AND LONDON BRIDGE BEACH RESTROOM IMPROVEMENTS

This project involves improving existing bathrooms at both locations and constructing a new bathroom at Rotary Beach Park.

PROJECT NO.
FA1060
STATUS
Construction
 
SCHEDULE
December 2018 to May 2019
COST
$1.6M
LOCATION
Rotary and London Bridge Beach Parks

LAKE HAVASU AVENUE RECONSTRUCTION PROJECT

This project is a reconstruction project which will provide a new waterline main, sidewalks, paved surface and raised medians.

PROJECT NO.
ST3270
STATUS
Construction
 
SCHEDULE
December 2018 to May 2019
COST
$3.5M
LOCATION
Lake Havasu Ave. from Mesquite Ave. to Swanson Ave.